Further update on the Sargent Beach Jetty and Breakwater project -
From Commissioner Mike Estlinbaum - Please keep in mind that this office doesn't sit on information that could be put out on timelines regarding all the projects coming to Sargent. We pass along information and/or updates as soon as we receive them. Furthermore, there isn't anything related to any of these projects sitting on my desk that could cause any delays. I turn around anything needed from this office or the county immediately. Unfortunately, we don't have any control how long things sit on a desk at agencies this office doesn't have any control over. All I can do is follow up regularly and ask if anything is needed from me. Having said that, I got an update on the breakwater project and a new timeline. Unfortunately the timeline has been delayed once again. This time only a couple of months. The new timeline is as follows: Advertise [go our for bid] 6/20/2025 Bid Opening 7/21/2025 Award* 8/29/2025 Issue Notice to Proceed 9/26/2025 Estimated Construction Comple...