So close - just waiting on contracts -

 From Bill Orton! 

I had a chance this week to visit with Rhonda Gregg the Project Director at Atkins regarding our Sargent Beach projects. Below is the information she provided me to share with all of you. Hopefully it will help as to where we are currently.
Thank you,
Bill Orton
We have our permits in hand for Sargent, and the Corps is going to partner with us and the GLO to use the dredge material from the Mouth of Colorado River as the sand source for the beach nourishment portion of the project. So a federal BUDM component to the beach nourishment aspect of the project.
We are waiting for contracts to come out of the GLO so that we can support the bid tasks for the breakwater portion of the project and CM for construction.
All the plans and specifications are complete.
Other than waiting- we are really positioned nicely.
All the funds are in place for construction of the project. (rock and sand)
The GLO and Corps have REALLY stepped up.
I couldn’t be more pleased for the county!!
Rhonda Gregg Hirsch
Project Director
Atkins

Comments

Popular posts from this blog

They had to rebid the Sargent Breakwater project

Update on the San Bernard - new notice of dredging

No New Update on Breakwater project - but a video of Mitchell’s Cut on 5/24/2024