Final requirements for Sargent Breakwater project -

Great details on the project on the Request for Proposal page for the Sargent Breakwater Project  - some interesting things on the construction of the breakwater and jetty at Mitchell's cut. Bids were due on October 25th so they are all in and being analyzed now. 

  • The breakwaters are 400 feet long and spaced 660 feet apart in 4 feet depth of water. The angled terminal groin at the inlet extends to a water depth of 8 feet. 
  • The goal of the project is to reduce beach erosion along Sargent Beach and the Matagorda Peninsula by stabilizing Sargent Beach and protecting the adjacent GIWW from erosional breaching. 
  • The approximate cost range for construction of the Project is $28,000,000 to $35,000,000. 
  • They will be staging at Mitchell's cut and using the road out to the cut to get equipment and supplies there
  • The jetty will be just shy of 1/2 mile long going from the cut into the Gulf
  • The staging areas will be secured - since one of the staging areas is the end of Mitchell cut - don't know what that means or what they will have to do to get access for heavy equipment down at Mitchell's cut.  
  • Here is the schedule - 
    • Evaluation Period October 31, 2023 to November 10, 2023 
    • Contractor Selection and Notice of Intent to Award November 13, 2023 
    • Contract Negotiation and Execution November 14, 2023 to December 11, 2023 
    • Deadline for Bonds and Insurance November 11, 2023 
    • Pre-Construction Conference and Notice to Proceed December 15, 202
Jetty plan

Breakwater plan






Comments

Popular posts from this blog

No New Update on Breakwater project - but a video of Mitchell’s Cut on 5/24/2024

More Delays in the Sargent Beach Stabilization project - 6 more months to go??

They had to rebid the Sargent Breakwater project